Evaluación del tiempo y costo en la propuesta de mejora de las alcantarillas de gran luz, en la carretera yurimaguas – munichis, provincia de alto amazonas, departamento de Loreto - 2020

Mostrar el registro sencillo del ítem

dc.contributor.advisor Ríos Vargas, Caleb
dc.contributor.author Rengifo Rodríguez, Noé
dc.contributor.author Vallejos Torres, Engelbert
dc.date.accessioned 2021-06-14T16:47:40Z
dc.date.available 2021-06-14T16:47:40Z
dc.date.issued 2021-03-29
dc.identifier.uri http://hdl.handle.net/20.500.14503/1303
dc.description.abstract El presente trabajo de investigación tiene como objetivo, Evaluar el tiempo y costo en la propuesta de mejora de las alcantarillas de gran luz en la carretera Yurimaguas – Munichis, provincia de Alto Amazonas, departamento de Loreto. Llegando entre otras a las siguientes conclusiones:  Presupuesto de la alcantarilla de gran luz según Expediente técnico: S/. 642,869.63. Presupuesto de la alcantarilla de gran luz, de acuerdo a la propuesta de mejora: S/. 622,363.40. Con esto podemos concluir que la propuesta de alcantarilla Doble SP MP152 Abovedada 38PA5-21, tiene un menor costo en S/ 20,506.23, respecto de la alcantarilla de gran luz considerada en el Expediente Técnico del Proyecto Bolt Plate Horizontal Elipse VR17. Esto debido al menor costo de la partida Suministro e Instalación de la alcantarilla, así como también el menor uso de relleno estructural.  Evaluando el segundo objetivo, Tiempo de ejecución entre el expediente Técnico y la Propuesta, concluimos que la alcantarilla del expediente técnico Bolt Plate Horizontal Elipse VR17, toma un tiempo de 30 días en ejecutarse, mientras que la propuesta Doble SP MP152 Abovedada 38PA5-21, toma un tiempo de 25 días en ejecutarse. Siendo esto una diferencia de 5 días. Cabe recalcar que este análisis se hace en relación de solo el proceso constructivo, ya que si incluimos los plazos de fabricación y entrega de materiales este podría representar una mayor diferencia. La alcantarilla del Expediente Bolt Plate Horizontal Elipse VR17, carece de demanda en el mercado actual por ser materiales importados y patentados, motivo por el cual el tiempo de fabricación e importación serían muy superior a diferencia de la alcantarilla Propuesta Doble SP MP152 Abovedada 38PA5-21, que son de fabricación nacional, lo cual también implicaría que, si llegara a presentarse alguna falla, este podría ser remplazado de forma más rápida el elemento dañado. es_ES
dc.description.abstract The objective of this research work is to evaluate the time and cost in the proposal to improve the high-light sewers on the Yurimaguas - Munichis highway, Alto Amazonas province, Loreto department. Reaching among others the following conclusions: • Budget for the large span sewer according to Technical File: S /. 642,869.63. Budget for the large light sewer, according to the improvement proposal: S /. 622,363.40. With this, we can conclude that the Double SP MP152 Vaulted 38PA5-21 culvert proposal has a lower cost in S / 20,506.23, compared to the large span culvert considered in the Bolt Plate Horizontal Elipse VR17 Project Technical File. This is due to the lower cost of the Supply and Installation of the culvert, as well as the lower use of structural fill. • Evaluating the second objective, Execution time between the Technical file and the Proposal, we conclude that the culvert of the Bolt Plate Horizontal Elipse VR17 technical file takes 30 days to execute, while the Double SP MP152 Vaulted 38PA5- 21 proposal, it takes a time of 25 days to execute. This being a difference of 5 days. It should be noted that this analysis is done in relation to only the construction process, since if we include the manufacturing and delivery of materials, this could represent a greater difference. The culvert of the File Bolt Plate Horizontal Elipse VR17, lacks demand in the current market because it is imported and patented materials, which is why the manufacturing and importing time would be much longer than the Proposed Double SP MP152 Vaulted culvert 38PA5-21, which are of national manufacture, which would also imply that, if a fault were to occur, the damaged element could be replaced more quickly. En_us
dc.description.uri Tesis es_ES
dc.format application/pdf es_ES
dc.language.iso spa es_ES
dc.publisher Universidad Científica del Perú es_ES
dc.rights info:eu-repo/semantics/openAccess es_ES
dc.rights.uri http://creativecommons.org/licenses/by-nc-nd/3.0/us/ *
dc.subject Alcantarillas de gran luz es_ES
dc.subject Pavimento rígido es_ES
dc.subject High span culverts En_us
dc.subject Rigid pavement En_us
dc.title Evaluación del tiempo y costo en la propuesta de mejora de las alcantarillas de gran luz, en la carretera yurimaguas – munichis, provincia de alto amazonas, departamento de Loreto - 2020 es_ES
dc.type info:eu-repo/semantics/bachelorThesis es_ES
thesis.degree.name Ingeniero Civil es_ES
thesis.degree.grantor Universidad Científica del Perú. Facultad de Ciencias e Ingeniería es_ES
thesis.degree.level Titulo Profesional es_ES
thesis.degree.discipline Ingeniería Civil es_ES
dc.subject.ocde https://purl.org/pe-repo/ocde/ford#2.01.00 es_ES
dc.publisher.country PE es_ES
renati.advisor.orcid https://orcid.org/0000-0002-7183-4892 es_ES
renati.advisor.dni 01115918 es_ES
renati.author.dni 70351581 es_ES
renati.author.dni 43025302 es_ES
renati.type https://purl.org/pe-repo/renati/type#tesis es_ES
renati.level http://purl.org/pe-repo/renati/level#tituloProfesional es_ES
renati.discipline 732267 es_ES
renati.juror Padilla Maldonado, Joel es_ES
renati.juror Samamé Zatta, Víctor Eduardo es_ES
renati.juror Cuzco Trigozo, Luis Armando es_ES


Ficheros en el ítem

El ítem tiene asociados los siguientes ficheros de licencia:

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess

Buscar en DSpace


Listar

Mi cuenta

Estadísticas