Evaluación del costo y tiempo de ejecución de las estructuras de contención tipo gaviones, ménsula y de gravedad, en la localidad de Alfonso Ugarte, distrito de Shamboyacu, provincia de Picota, departamento de San Martín

dc.contributor.advisorMartínez Quiróz, Enrique Napoleón
dc.contributor.authorRamírez Rodríguez, Luiggi Reninger
dc.contributor.authorPintado Celiz, Carlos Fidel
dc.date.accessioned2023-04-21T14:48:21Z
dc.date.available2023-04-21T14:48:21Z
dc.date.issued2022-12-19
dc.description.abstractEl presente proyecto de investigación tiene por objetivo principal evaluar el costo y tiempo de ejecución de las estructuras de contención tipo gaviones, ménsula y de gravedad, en la localidad de Alfonso Ugarte, distrito de Shamboyacu, provincia de Picota, departamento de San Martín. Para lograr estos resultados, se han empleado metodologías de investigación como es el tipo descriptivo cuyo esquema está dedicado a la evaluación del costo y tiempo en la ejecución de las estructuras de contención del tipo gavión, ménsula y gravedad. Con respecto a la evaluación del costo se tomó en cuenta los estudios de suelos, ubicación de cantera de rocas, planos, metrados, precios de mano de obra en base a capeco 01-05-2022 AL 31-05-2023, precios de insumos y maquinaria en base a los precios de mercado, donde además se tuvo en cuenta los cálculos de flete de materiales, movilización y desmovilización de maquinarias y equipos. Los resultados de la variación de costos entre el muro de gaviones (285,537.44) y ménsula (292,197.01) es de 6,659.57, siendo mínima la diferencia. Por lo tanto, se podría decir que realizar un muro de gavión es más económico. Los resultados de la variación de costos entre el muro de gaviones (285,537.44) y gravedad (306,191.90) es de 20,654.46. Por lo tanto, se podría decir que realizar un muro de gavión es más económico. Los resultados de la variación de costos entre el muro de ménsula (292,197.01) y gravedad (306,191.90) es de 13,994.89. Por lo tanto, se podría decir que realizar un muro de ménsula es más económico. Los resultados de la variación en el tiempo de ejecución entre un muro de gavión (46 d.c.) y ménsula (56 d.c.) es de 10 d.c. Por lo tanto, se podría decir que ejecutar un muro de gavión se emplea menos tiempo que ejecutar un muro de “EVALUACIÓN DEL COSTO Y TIEMPO DE EJECUCIÓN DE LAS ESTRUCTURAS DE CONTENCIÓN TIPO GAVIONES, MÉNSULA Y DE GRAVEDAD, EN LA LOCALIDAD DE ALFONSO UGARTE, DISTRITO DE SHAMBOYACU, PROVINCIA DE PICOTA, DEPARTAMENTO DE SAN MARTÍN” 10 ménsula. Los resultados de la variación en el tiempo de ejecución entre un muro de gavión (46 d.c.) y gravedad (56 d.c.) es de 10 d.c. Por lo tanto, se podría decir que ejecutar un muro de gavión se emplea menos tiempo que ejecutar un muro de gravedad. Con respecto a la ejecución de muros de ménsula y gravedad, tomaría el mismo tiempo. Finalmente, el costo beneficio que genera este proyecto de investigación es que, si a criterio del proyectista se requiere ahorrar tiempos y plazos es conveniente ejecutar muros de gaviones, ya que es económico y se ejecutará en menos tiempo.es_ES
dc.description.abstractThe main objective of this research project is to evaluate the cost and execution time of gabion, bracket and gravity type retaining structures in the town of Alfonso Ugarte, district of Shamboyacu, province of Picota, department of San Martin. To achieve these results, research methodologies have been used, such as the descriptive type whose scheme is dedicated to the evaluation of the cost and time in the execution of gabion, bracket and gravity type retaining structures. With respect to the evaluation of the cost, we took into account the soil studies, location of the rock quarry, plans, metrics, labor prices based on capeco 01-05- 2022 TO 31-05-2023, prices of inputs and machinery based on market prices, where we also took into account the calculations of freight of materials, mobilization and demobilization of machinery and equipment. The results of the cost variation between the gabion wall (285,537.44) and the bracket (292,197.01) is 6,659.57, being the difference minimal. Therefore, it could be said that building a gabion wall is more economical. The results of the cost variation between the gabion wall (285,537.44) and gravity (306,191.90) is 20,654.46. Therefore, it could be said that a gabion wall is more economical. The results of the cost variation between the cantilever wall (292,197.01) and gravity (306,191.90) is 13,994.89. Therefore, it could be said that the cantilever wall is more economical. The results of the variation in the execution time between a gabion wall (46 d.c.) and cantilever (56 d.c.) is 10 d.c. Therefore, it could be said that executing a gabion wall takes less time than executing a cantilever wall.En_us
dc.description.uriTesises_ES
dc.formatapplication/pdfes_ES
dc.identifier.urihttp://hdl.handle.net/20.500.14503/2370
dc.language.isospaes_ES
dc.publisherUniversidad Científica del Perúes_ES
dc.publisher.countryPEes_ES
dc.rightsinfo:eu-repo/semantics/openAccesses_ES
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/3.0/us/*
dc.subjectCostoses_ES
dc.subjectTiempo de ejecuciónes_ES
dc.subjectPresupuestoses_ES
dc.subjectEstructura de contenciónes_ES
dc.subjectGavioneses_ES
dc.subjectMénsulaes_ES
dc.subjectGravedades_ES
dc.subjectCostEn_us
dc.subjectTime of executionEn_us
dc.subjectBudgetsEn_us
dc.subjectContainment StructuresEn_us
dc.subjectGabionsEn_us
dc.subjectCorbelEn_us
dc.subjectGravityEn_us
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.00es_ES
dc.titleEvaluación del costo y tiempo de ejecución de las estructuras de contención tipo gaviones, ménsula y de gravedad, en la localidad de Alfonso Ugarte, distrito de Shamboyacu, provincia de Picota, departamento de San Martínes_ES
dc.typeinfo:eu-repo/semantics/bachelorThesises_ES
renati.advisor.dni00953065es_ES
renati.advisor.orcidhttps://orcid.org/0000-0002-5965-9892es_ES
renati.author.dni75149557es_ES
renati.author.dni70880902es_ES
renati.discipline732267es_ES
renati.jurorRíos Vargas, Calebes_ES
renati.jurorCuzco Trigozo, Luis Armandoes_ES
renati.jurorAlva Arévalo, Albertoes_ES
renati.levelhttp://purl.org/pe-repo/renati/level#tituloProfesionales_ES
renati.typehttps://purl.org/pe-repo/renati/type#tesises_ES
thesis.degree.disciplineIngeniería Civiles_ES
thesis.degree.grantorUniversidad Científica del Perú. Facultad de Ciencias e Ingenieríaes_ES
thesis.degree.levelTitulo Profesionales_ES
thesis.degree.nameIngeniero Civiles_ES

Files

Original bundle

Now showing 1 - 1 of 1
Thumbnail Image
Name:
LUIGGI RENINGER RAMÍREZ RODRÍGUEZ Y CARLOS FIDEL PINTADO CELIZ - TESIS.pdf
Size:
12.79 MB
Format:
Adobe Portable Document Format
Description:
Texto completo

License bundle

Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.3 KB
Format:
Item-specific license agreed upon to submission
Description:

Collections